Plan before opening assemblies
The work plan identifies the contaminant, extent, occupants, dispersion paths, waste, emergency stops and closure criteria.
- Scope and zones
- Containment
- Pressure and filtration
- PPE and decontamination
- Transport and disposal
Execute under control
Methods are contaminant-specific. Asbestos, mould, lead dust and water damage do not use the same work rule or evidence.
- Work log
- Barrier monitoring
- Dust control
- Content protection
- Deviations and corrective action
Use independent verification when risk requires it
Closure combines visual inspection, source correction, cleanliness, justified measurement or analysis and document review.
- Source controlled
- Materials treated
- Area clean and dry
- Acceptable results
- Return-to-service report